What we are building, in order

Orbeex ships in phases. Each phase has a clear exit criterion, and nothing is claimed as done before it is.

  1. P0

    Foundation and validation

    weeks 0–6

    active
  2. P1

    Core engine MVP

    weeks 6–20

    planned
  3. P2

    Desktop application

    weeks 20–34

    planned
  4. P3

    AI-native layer

    weeks 28–44

    planned
  5. P4

    Web / WebAssembly

    weeks 40–52

    planned
  6. P5

    Plugin ecosystem

    weeks 48–60

    planned
  7. P6

    Enterprise hardening

    weeks 56–72

    planned
  8. P7

    General availability

    weeks 72–84

    planned

Weeks are illustrative targets, not commitments. This page is updated as the plan changes.